TL;DR
The US Senate advanced BAAJA, a bipartisan permitting reform bill that would fast-track energy and data center construction, but a fierce backlash from environmental groups, tribal nations, and voters who turned against data centers in the 2026 midterms is threatening its passage before January.
What happened
- The Senate voted to advance the Bipartisan American Affordability and Jobs Act (BAAJA), a 417-page permitting reform bill, in November 2026.
- The bill streamlines environmental and judicial reviews for energy projects including gas pipelines, transmission lines, and data center infrastructure on public and federal lands.
- Data centers drawing over 20 MW from the grid would be required to pay associated upgrade costs, estimated at roughly $55 billion over ten years, about $35 billion more than under current policy.
- At least 17 active applications for data center campuses on public land span thousands of acres across Arizona, Idaho, Nevada, and other states.
- US gas projects powering data centers surged from roughly 4 gigawatts in early 2024 to 189 gigawatts in development by mid-2026, per Global Energy Monitor data.
Why it matters
- Anti-data center sentiment shaped the 2026 midterms, making BAAJA a direct political liability for Democrats who must balance affordability, clean energy, and constituent opposition.
- Stripping back Clean Water Act and Endangered Species Act protections could fast-track gas-powered campuses like the Ports-Pike Technology Campus in Ohio and the STAK Energy Campus in Alaska.
- A coalition of tribal nations warns the bill would gut protections for historic and cultural sites threatened by federally connected data center projects.
- Nearly 200 advocacy groups, including the Sierra Club and NRDC, oppose the bill, calling it a backdoor subsidy for fossil fuels and Big Tech.
- NERC's 2026 forecast identifies data centers as the primary driver of historically unprecedented electricity demand growth, meaning inaction also carries real infrastructure risk.
What to watch next
- Whether Democrats hold together or fracture before the current Congress ends in January 2026, given the bill's collision with midterm voter mandates.
- Whether Trump administration commitments to restore regular permitting order for wind and solar projects materialize with enough specificity to bring skeptical Democrats on board.
- Progress on specific gas-powered projects like Ports-Pike and STAK Energy Campus, which would signal whether BAAJA's fast-track provisions are being used as critics fear.
Originally published on Present of AI, a daily source-linked AI news timeline. Read the full timeline or browse the open dataset.